The water well contractor has experienced some downhole issues that have required him to remobilize and correct these issues. The current 24-hour operations are expected to last approximately one more week. When this is completed, there should be a break in the 24-hour operations for one to two weeks while equipment is reinstalled in the well. After this time, the contractor will develop the well, a process that will take approximately two weeks and will involve intermittent operations, most notably one pumping test that must run for 30 hours continuously.
If you have any questions, please contact Kevin Gilligan with BGE, Inc. (District Engineer for HCMUD 412 and HCMUD 504) at 713-488-8192.
Please monitor the Harris County MUD 412 website for future updates.